Project background and origin
Due to the increasing public and industrial water consumption in the Hsinchu area, According to the Taiwan Water Corporation’s estimate that the water consumption in Hsinchu area should increase 198,000 CMD in 2006.In 1989 The Water Resources Agency estimate that the original water source and water consumption can only be maintained until 1998.
In order to solve the water dilemma and support the long-term economic development in Hsinchu, The Taiwan Provincial Water Resources Bureau Planning Team (predecessor of the Institute) conducted preliminary exploration of the Second Baoshan Reservoir in 1986. Initial planning began in 1989. Made feasibility studies in 1993. "The Project Plan for the Second Baoshan Reservoir in Hsinchu County" was proposed in 1995(the location of the reservoir is shown in Fig. 1). It was built by the Taiwan Water Resources Bureau (predecessor of the Water Resources Agency), the Taiwan Water Corporation and the Hsinchu County Government. It began construction in April 1997 and completed in June 2006.
Second Baoshan Reservoir is located in Shanhu Village, Baoshan Township, Hsinchu County. It features an off-stream reservoir densign, and obtains excess water diverted from the Shang-ping River, which is a tributary of the Touqian River. After the sand sinking in the sediment silting basin, the water is Transbasin Diversion into the reservoir for storage and utilization.
Summary of major developments in the project
A summary of the major milestones of the project is shown in Fig. 2.
Planning process and results
Water Resources Planning Institute conduct Planning situation
Water Resources Planning Section planned the project. Geo-Tech Research Section Handled dam material survey, geological exploration, topographic survey, etc (Fig. 3).
Planning process plan
- Dam site plan
The Institute conducted a survey on the water source development of Fengshan river and Touqian river in 1986. After three years of investigation and selection of seven possible dam sites, chose two possible dam sites. Two possible dam sites were evaluated in 1991. Because the dam site has less dam filling, the inundation area was simpler and the raw water cost was lower. (16.38 TWD / ton), so the current Baoshan Second Reservoir dam site was selected. - Transbasin Diversion weir plan
There are two original plans for the weir plan. As shown in Fig. 4, the first plan is to use the existing dry trees weir to block the river rafts and increase the water intake at the inlet; the second plan is to build a new river at about 350 meters upstream. After assessing the difficulty of the construction of the newly built barrage and the difficulty of maintaining the deep flume, the first plan was adopted. - Water source application plan
The original plan of the reservoir was to supply water for the Hsinchu area by a single reservoir, which was about 191,500 CMD. After considering the joint use with other reservoirs, the planning “Evaluation of Conjunctive Operation of Baoshan Reservoir, Baoshan Second Reservoir and Longern Weir” was conducted in 1996. The joint use of Longen and Baoshan Reservoirs increased the system water supply to 282,000 CMD.
Data and graph
The major project data and photos of the completed Baoshan Second Reservoir are shown in Figs. 5 and 6.