Skip to main content

Project summary

In 1980, due to the difficulties of economic development, and the problem of water demand in Yunlin area, the Water Resources Planning Institute took charge of the “Small and Medium Reservoir Planning in Yunlin Area”, and investigated the comprehensive exploration of water resources in Yunlin, finally completed the planning of small and medium-sized reservoirs in Yunlin area. In 1992, for the purpose of the public water in Yunlin area and the urgent needs for industrial water of the Sixth Naphtha Cracker and Yunlin Outlying Islands Industrial Zone, the reservoir water resources development survey in Yunlin area were carried out, and the feasibility planning of Hushan and Hunan Reservoirs in Yunlin County was completed in 2000.

This project was approved by the Executive Yuan in 2001. The total budget is about NTD16.244 billion. The dam construction was completed on 5th July 2014. The reservoir began to store water on 2nd April 2016, and began to operate on 5th July 2016. The location of the reservoir is in Fig. 1.

Major events


Table 1: The major events of the Hushan Reservoir
1992
The Xiluo engineering team was established.
2000
The environmental report of Hushan and Hunan Reservoirs Project was approved by the Environmental Protection Administration.
2001
The Executive Yuan approved the Hushan and Hunan Reservoirs Project. In the same year, the Executive Yuan agreed to rename the "Hushan and Hunan Reservoirs Project" as "Hushan Reservoir Project".
2002
The Hushan Reservoir Project was approved for development by the Ministry of the Interior.
2004
The member of the Control Yuan went to the Hushan Reservoir to observe the protective forest canceling problem and the Fairy Pitta conservation problem.
2006
The estimates of Hushan Reservoir Project in 2006 were approved by the Legislative Yuan.
2008
Guiding the water of the Nanshenkeng River into Hunan Dam Tunnel was completed.
2011
The Environmental Protection Administration won the lawsuit of the Hushan Reservoir Project.
2014-2015
The headrace construction of the Hushan Reservoir Dam Project was completed.
2016
The Hushan Reservoir Management Center was established on 6th January 2016.
The pipeline test of the downstream of the Hushan Reservoir was completed on 9th August 2016.
The Hushan Reservoir began to store water on 2nd April 2016.
The Hushan Reservoir began to operate on 5th July 2016.

Planning process and results

The work team of planning

The Hushan Reservoir planning was conducted by the Water Resources Planning Institute, the Hydrotech Research Section assisted with the hydraulic model test, the River Management Section operated downstream river improvement, the Geotech Research Section and the Central Geological Survey executed dam material investigation, geological survey and drilling. Related content is shown in Fig. 2.

The process of planning

  1. Dam location plan
    1. The Hushan main dam

      The Hushan reservoir is an off-stream reservoir. In addition to the runoff from the catchment, we use the Tongtou Weir to obtain water from the Qingshui River. The height of the main dam is 75 meters, the elevation is 215 meters, and the width of the dam is 570 meters.

    2. The Hushan minor dam

      The Hushan minor dam is located in the southwest of the main dam.

    3. The Hunan dam

      After the suggestion of investigation and planning team in May 1994, it proposed to make the dam axis of Hushan main dam, Hushan minor dam and Hunan dam connected into a line, as shown in Fig. 3.

  2. The transbasin water diversion project

    There are six options for the trans-basin water diversion project. The routes of the diversion projects are along the river line, as shown in Fig. 4. After evaluation, the option 5 is selected.

  3. Planning profiles

    The relevant dam and weir data are shown in Table 2. The layout plan is detailed in Fig. 5. After the reservoir is completed, the completed view of Hushan Reservoir is in Fig. 6.

Construction
Item
Content
Table 2: Profiles
Reservoir
Catchment area
6.58 square kilometers
Full water level
EL.211.5 meters
Full water level area
2.018 hectares
Reservoir minimum elevation
EL.165.0 meters
Water storage
53.47 million cubic meters
Dam
Dam type
Central clay core zone and rolling stone dam
Dam top elevation
EL.216 meters
Dam top length
The Hushan main dam: 578 meters
The Hushan minor dam: 334 meters
The Hunan dam: 609 meters
Dam top width
10 meters
Maximum height of the dam
75 meters
Dam volume
12.797 million cubic meters
Spillway
Type
Spillway connected with
water purification pool
Flood discharge
509 cms
Dome elevation
EL.211.5 meters
Water intake
Water intake type
Oblique Layering
Water intake elevation
EL.180、165 meters
Water intake discharge
  1. Public water supply channel 12.27 cms
  2. The river discharges 1.00cms
Cross-territorial water diversion facilities
Barrage
  1. Location: move down 40 meters
  2. Type: straight down
  3. Elevation: EL.222 meters, Length: 91 meters
  4. Water intake: 20cms
  5. Flood discharge: 6,530 cubic meters / sec
Cross-territorial water diversion channel
  1. Open channel: 85 meters, Closed conduit: 56 meters, Inverted siphon: 126 meters, PCCP: 618 meters, tunnel: 2,825 meters
  2. Water diversion volume: 20cms
Downstream connecting pipe
  1. Water purification plant: add the pretreatment equipment of Linnai and Hushan water purification plant
  2. Infuse into the pre-processing pool